A Performance-Based Design Brief (PBDB) is the agreed brief that defines how a Performance Solution will be developed, assessed and documented under the National Construction Code (NCC). It records the project objectives, applicable Performance Requirements, design fire scenarios, acceptance criteria, Assessment Methods and stakeholder roles. Since NCC 2022, preparing a PBDB is a required step for every Performance Solution, so everyone is aligned before detailed fire engineering work begins.
What is a Performance-Based Design Brief under the NCC?
In NCC 2022 Volume One, a Performance-Based Design Brief is a mandatory step in developing any Performance Solution under clause A2G2(4), and is most commonly prepared by fire safety engineers for fire safety Performance Solutions. The PBDB sits at the start of the process and sets out what will be analysed, how it will be analysed, and what outcomes must be demonstrated to show that the Performance Requirements are satisfied.
For fire safety, the PBDB is typically prepared in accordance with the Australian Fire Engineering Guidelines (AFEG). It is a collaborative document rather than a calculation report, and it is used for any fire safety Performance Solution, whether relatively simple (for example, an extended travel distance) or more complex (for example, an atrium smoke control system).
Why is a Performance-Based Design Brief required?
The NCC allows compliance using either the Deemed-to-Satisfy Provisions or a Performance Solution. When a Performance Solution is used, there is no single prescriptive “recipe” to follow, so a structured and transparent process is needed to demonstrate that the relevant Performance Requirements are met.
The PBDB helps to:
- Clearly identify which NCC Performance Requirements and Deemed-to-Satisfy Provisions are relevant.
- Define project-specific fire safety objectives and acceptance criteria.
- Agree the Assessment Methods (Evidence of Suitability, Verification Methods, Expert Judgement or Comparison with the Deemed-to-Satisfy Provisions) and the analysis tools to be used, such as fire, smoke or egress modelling.
- Document assumptions, limitations and responsibilities before detailed analysis starts.
- Provide a reference for the building certifier, fire brigade (where applicable) and other stakeholders when assessing the final Fire Engineering Report.
Under NCC 2022, preparing a PBDB in consultation with relevant stakeholders is a required step in the Performance Solution process, not an optional extra. In New South Wales, consultation with Fire and Rescue NSW is also a regulated part of many fire safety Performance Solutions and is generally integrated into the PBDB discussions.
When do you need a Performance-Based Design Brief?
You need a PBDB whenever a Performance Solution is proposed instead of, or in addition to, a DTS Solution. Common fire safety triggers include:
- Features not expressly covered by the Deemed-to-Satisfy Provisions (for example, large atria, interconnected fire compartments or uncommon layouts).
- Departures from prescriptive DTS requirements (for example, extended travel distances, alternative exit arrangements, or reduced Fire Resistance Levels subject to justification).
- Complex buildings where strict DTS compliance is impractical, such as major hospitals, large shopping centres, transport interchanges or mixed-use towers.
- Upgrades and refurbishments where existing building constraints make full DTS compliance difficult.
The scale of the PBDB should be proportionate to the complexity and risk of the proposed Performance Solution. A simple, low-risk departure may need only a concise PBDB, while complex projects typically require a detailed PBDB workshop and document.
What does a Performance-Based Design Brief include?
While formats vary, a well-prepared PBDB will usually include the elements below, adapted from the AFEG process.
| PBDB element | What it typically covers |
|---|---|
| Project description | Building classification(s), size, height, use, key features, staging and occupancy characteristics. |
| Stakeholders | Building owner, developer, architect, fire safety engineer, building certifier or surveyor, builder, relevant authority and, where required, the fire brigade. |
| Objectives | Objectives linked to the NCC Performance Requirements (occupant safety, fire brigade intervention, limiting fire spread to other property), plus any additional client objectives such as property protection or business continuity. |
| Applicable NCC provisions | Relevant Performance Requirements and the Deemed-to-Satisfy Provisions being varied or replaced by the Performance Solution. |
| Design fires and scenarios | Credible fire scenarios, locations and design fires selected for analysis, reflecting building use and risk. |
| Acceptance criteria | Quantitative or qualitative criteria used to judge performance (for example, tenability limits, evacuation times, smoke layer heights). |
| Assessment Methods | Which NCC Assessment Methods will be used, and the supporting analysis tools (for example, fire and smoke modelling, egress analysis). |
| Input data and assumptions | Geometry, material properties, fire load, occupant numbers and characteristics, active system performance and reliability assumptions. |
| Management and operation | How the building is expected to be operated and maintained. Management procedures are supplementary, not the primary means of compliance. |
| Documentation and reporting | Deliverables (for example, the Fire Engineering Report), format, review stages and sign-off responsibilities. |
The PBDB is usually signed or endorsed by key stakeholders to record agreement on scope and method, acknowledging that detailed results will follow in the Fire Engineering Report.
How does a PBDB fit into the Performance Solution process?
NCC 2022 clause A2G2(4) sets out the steps for developing a Performance Solution, and the AFEG describes how to carry them out for fire safety. The PBDB anchors the first step and shapes everything that follows.
1. Prepare the Performance-Based Design Brief with stakeholders
The fire safety engineer convenes the PBDB process with the relevant parties, through a workshop or a series of meetings. The aims are to:
- Clarify the proposed Performance Solution(s) and why they are needed.
- Agree the statement of the problem and the objectives.
- Identify the applicable Performance Requirements.
- Select design fire scenarios and acceptance criteria.
- Agree the Assessment Methods and required input data.
- Confirm documentation expectations and consultation steps, including any mandatory fire brigade involvement.
The output is the written PBDB, which becomes the road map for the analysis.
2. Carry out the analysis in accordance with the PBDB
With the PBDB agreed, the fire safety engineer undertakes the detailed analysis. Depending on the project, this may involve:
- Applying NCC Verification Methods, or other Verification Methods accepted by the appropriate authority.
- Fire and smoke modelling using appropriate software tools.
- Egress and evacuation analysis, using calculations and, where justified, computer models.
- Comparison with the Deemed-to-Satisfy Provisions to show the Performance Solution is at least equivalent to a DTS Solution.
- Expert Judgement from suitably qualified and experienced practitioners.
Throughout this stage, the engineer works to the assumptions, scenarios and criteria in the PBDB. Material changes are discussed with stakeholders and documented as a PBDB update or explained in the final report.
3. Evaluate results against the acceptance criteria
The analysis results are checked against the acceptance criteria in the PBDB. For example, if tenability criteria were set for occupied paths of travel, the model outputs are tested against those limits for each design fire.
If results do not meet the criteria, the design may need refinement (for example, additional smoke exhaust, changed compartmentation or adjusted egress provisions) and the analysis is repeated until the criteria are met or the Performance Solution is reconsidered.
4. Prepare the Fire Engineering Report
The final step is documentation, usually a Fire Engineering Report. This report should:
- Summarise the building and the proposed Performance Solution(s).
- Reference the PBDB and confirm how its requirements were followed.
- Describe the methods, inputs, assumptions and limitations.
- Present the analysis results in a clear, traceable way.
- Demonstrate how the Performance Requirements are satisfied.
- Define any conditions of use, maintenance requirements and interactions with other building systems.
The Fire Engineering Report, together with the PBDB and supporting material, is then used by the building certifier or relevant authority to assess the Performance Solution as part of the building approval.
Who is involved in developing a Performance-Based Design Brief?
Participants vary by project and jurisdiction, but commonly include:
- Building owner or developer – confirms project objectives, operational intent and risk appetite.
- Architect and design team – explain the design, constraints and proposed departures from the Deemed-to-Satisfy Provisions.
- Fire safety engineer – leads the PBDB process, proposes analysis methods and prepares the PBDB and Fire Engineering Report.
- Building certifier or surveyor – indicates approval expectations, relevant NCC provisions and documentation requirements.
- Builder or project manager – advises on constructability, staging, programme and temporary conditions.
- Facility manager or operator – provides insight into occupancy patterns and management practices.
- Fire brigade – consulted for fire safety Performance Solutions in many states and territories, particularly NSW, and may provide operational input.
Early, meaningful participation tends to reduce later design changes, because key assumptions and criteria are agreed upfront rather than debated at the approval stage.
How does a PBDB relate to NCC Assessment Methods?
The NCC recognises four Assessment Methods for determining compliance with the Performance Requirements: Evidence of Suitability, Verification Methods, Comparison with the Deemed-to-Satisfy Provisions, and Expert Judgement. A Performance Solution can use one or a combination of these.
The PBDB specifies which Assessment Methods will be used and how. For example:
- Using a Verification Method for smoke control design, with defined design fires and modelling approaches.
- Comparing evacuation times for a proposed exit arrangement against a DTS-compliant arrangement.
- Relying on Evidence of Suitability for specific products or systems, such as test reports or a CodeMark Certificate of Conformity.
- Documenting Expert Judgement from a suitably qualified fire safety engineer where formal methods are not practical.
Capturing this in the PBDB means everyone understands the basis on which compliance will be demonstrated before the analysis starts.
Common mistakes to avoid with Performance-Based Design Briefs
- Treating the PBDB as a formality – a minimal document without genuine consultation can lead to disagreements about objectives, scenarios or criteria late in the project.
- Missing relevant Performance Requirements – overlooking clauses can leave the Performance Solution incomplete and require re-analysis.
- Relying too heavily on management procedures – treating staff actions as the main safeguard instead of robust passive and active fire safety measures.
- Vague acceptance criteria – qualitative language without measurable criteria makes compliance hard to demonstrate.
- Late stakeholder involvement – involving the certifier, operator or fire brigade too late can result in unexpected objections.
- Not updating the PBDB – after major design changes, the PBDB may need review so the analysis stays aligned with the design.
Practical tips for building professionals
- Engage a fire safety engineer early – ideally at concept design, before layouts are locked in.
- Be clear about non-NCC objectives – if you have property protection, resilience or insurance-driven goals, ask for them to be recorded in the PBDB.
- Allow time for consultation – PBDB workshops for larger or unusual buildings need time for preparation and review.
- Check alignment with other disciplines – make sure PBDB assumptions match the mechanical, electrical and structural design, especially for smoke control, detection and fire resistance.
- Keep records – retain the PBDB, sign-offs and related correspondence; they explain the design basis for future refurbishments and audits.
Frequently Asked Questions
Is a Performance-Based Design Brief mandatory for every Performance Solution?
Yes. Since NCC 2022, clause A2G2(4) requires a Performance-Based Design Brief to be prepared in consultation with relevant stakeholders for every Performance Solution. The level of detail should be proportionate to the complexity and risk of the solution, so a simple departure may need only a concise PBDB.
How early should a PBDB be prepared?
A PBDB is best prepared during concept or early design, once the building form and major uses are understood but before detailed documentation is complete. Starting too late can restrict design options and lead to rework if the agreed criteria require changes to layouts or systems.
Does a PBDB guarantee that my Performance Solution will be approved?
No document can guarantee approval. A PBDB clarifies expectations and methods upfront, which typically reduces the risk of major surprises. Final acceptance rests with the building certifier and relevant authorities, based on the completed Fire Engineering Report and the overall design.
Can the PBDB be changed once analysis has started?
Yes. If assumptions, design features or objectives change, the PBDB can be updated. Significant changes should be discussed with stakeholders and documented, so the audit trail from brief to Fire Engineering Report remains transparent.
Key takeaways
- A Performance-Based Design Brief is the agreed road map for developing and assessing a Performance Solution under the NCC.
- Since NCC 2022, a PBDB is a required step for every Performance Solution (clause A2G2(4)).
- The PBDB captures objectives, applicable NCC provisions, fire scenarios, acceptance criteria and Assessment Methods, and is developed with key stakeholders.
- A clear PBDB supports a robust Fire Engineering Report and helps certifiers and authorities assess the Performance Solution.
- Engaging a fire safety engineer early and investing in a thorough PBDB can reduce later design changes, delays and uncertainty.
How Quench Fire Engineers Can Help
Quench Fire Engineers provides fire safety engineering services across Australia, delivering practical, compliant and cost-effective solutions for commercial, residential, industrial, healthcare and mixed-use developments.
Our services include:
- Fire Engineering Reports and Performance Solutions
- Performance-Based Design Briefs
- Fire Safety Strategies
- Fire Sprinkler and Drencher System Design
- Fire Hydrant and Ring Main Design
- Fire Authority Consultation
- Peer Review and Certification
- Building Notices and Orders
- Expert Witness Reports
To discuss your project, contact our team or call +61 497 100 066.
This article provides general information only and does not constitute professional advice for any specific project. Requirements vary by jurisdiction, building classification and project circumstances. Always obtain project-specific advice from a qualified fire safety engineer and confirm requirements with your building certifier and the relevant authorities.